|
United States Environmental
Protection Agency Region
V POLLUTION REPORT |
| Date: |
Monday, August 06, 2007 |
| From: |
James Augustyn/Brian Schlieger, On-Scene
Coordinator |
|
Subject: |
Tittabawassee River Project Reach D Tittabawassee River Dioxin-Reach D Midland, MI
Latitude: 43.6011 Longitude: -84.2386
|
| POLREP No.: |
3 |
Site #: |
B5KF |
| Reporting Period: |
7-27-07 to 8-03-07 |
D.O. #: |
|
| Start Date: |
7/9/2007 |
Response Authority: |
CERCLA |
| Mob Date: |
7/9/2007 |
Response Type: |
Time-Critical |
| Completion Date: |
|
NPL Status: |
Non NPL |
| CERCLIS ID #: |
MID980994354 |
Incident Category: |
Removal Action |
| RCRIS ID #: |
|
Contract # |
|
|
On July 9, 2007, Dow’s contractor began positioning equipment on
a work barge to begin the preparation of driving temporary sheet
piling in the river to delineate the area of highest dioxin
contamination. Dow’s contractor has completed
construction on the HDPE sediment transport pipeline and has
conducted hydrostatic testing of the line. The sediment transport
line is approximately 9,000 feet long and will transport sediment
slurry from the dredge area in the river to the Geo-Tube dewatering
cell.
On-Scene Coordinators (OSC) Jim Augustyn and Brian
Schlieger are providing oversight with assistance from U.S. EPA’s
START Contractor, Weston Solutions,
Inc.
|
|
The following tasks have been completed by Dow’s contractors
during the period of July 28 to August 3, 2007:
Saturday July
28th, Dow’s contractor completed installing a sheet pile turbidity
barrier up stream of the pipe bridge in preparation for excavation
of rip rap along the RGIS system. Air monitoring throughout the
project area continued. Work activities at the
containment cell included: site grading and restoration, survey and
grade control, HDPE pipe welding, installation of odor control
piping, installation of electrical infrastructure for each
containment cell, dust and track-out control, and miscellaneous
house-keeping activities.
Monday July 30th, Installation and
driving of the temporary sheet piling turbidity barrier continued in
the river. Excavation and transportation of rip rap
materials along the RGIS system to Dow’s Salzburg Landfill
began. Air monitoring throughout the project area
continued. A second crew began preparation for sheet
piling installation under the bridge. Dow’s contractor
began collecting background turbidity data from a temporary monitor
located upstream from the project area. Work activities
at the containment cell continued.
Tuesday July 31st,
Installation and driving of the temporary sheet piling turbidity
barrier under the bridge continued. Excavation,
transportation, and disposal of rip rap materials
continued. Dow’s contractor continued collecting
background turbidity data from a temporary monitor located upstream
of the project area and began data collection downstream of the
Reach D work area. Work activities at the containment
cell continued.
Wednesday August 1st, Installation and
driving of the temporary sheet piling turbidity barrier under the
bridge continued in the river and excavation and transportation of
rip rap materials to Dow’s Salzburg Landfill
continued. Dow’s contractor continued collecting
background turbidity data from temporary turbidity monitors located
upstream and downstream of the project area. Work activities at the
containment cell continued.
Thursday August 2nd, Dow’s
contractor installed temporary sheet piling underneath the piping
bridge. Excavation and transportation of rip rap
materials to Dow’s Salzburg Landfill continued. Air
monitoring throughout the project area continued as well as
turbidity data collection. Work activities at the
containment cell continued.
Friday August 3rd, Installation
and driving of the temporary sheet piling turbidity barrier
continued in the river and excavation and disposal of rip rap to
Dow’s Salzburg Landfill continued. Air monitoring
throughout the project area continued. Dow’s contractor
continued collecting background turbidity data from turbidity
monitors located upstream and downstream of the project
area. Work activities at the containment cell continued.
|
|
Sheet piling will be driven down to established elevations to
complete the installation of the turbidity barrier above the Dow
bridge. Permanent Turbidity monitors will be placed in
the river to monitory potential increases in turbidity that may
result from excavation and dredging operations.
Rip rap and
large debris will continue to be mechanically excavated from the
existing RGIS sheet piling within the turbidity barrier
area. The excavated material will be placed over the RGIS
system and allowed to drain. Once sufficiently free of
water, the excavated material will be transported to Dow’s Salzburg
Road Landfill for disposal.
Construction on the containment
cell will continue. Geo-Tubes and associated connections
to the sediment transport line will be completed in preparation for
dredging operations to start. Installation of the temporary
turbidity barrier under the Dow bridge to the Dow Dam will
continue.
|
|
Once all rip rap and large debris is removed from the work area,
installation of new permanent sheet piling for the RGIS system will
begin. Dredging of contaminated sediment cannot begin
until the permanent sheet piling is in place.
The
second sheet piling crew will continue to install temporary sheet
piling and will place another section under Dow's 'Railroad'
bridge. The temporary sheet piling will be installed
along the entire length of the project area and will end adjacent to
the Dow Dam.
|
| |
Budgeted |
Total To Date |
Remaining |
% Remaining |
|
Extramural Costs
|
| RST/START |
$120,000.00 |
$25,000.00 |
$95,000.00 |
79.17% |
|
Intramural Costs
|
| |
| Total Site
Costs |
$120,000.00 |
$25,000.00 |
$95,000.00 |
79.17% |
* The above accounting of expenditures is an estimate based
on figures known to the OSC at the time this report was written. The OSC
does not necessarily receive specific figures on final payments made to
any contractor(s). Other financial data which the OSC must rely upon may
not be entirely up-to-date. The cost accounting provided in this report
does not necessarily represent an exact monetary figure which the
government may include in any claim for cost recovery.
epaosc.net/tittabawasseeDioxinReachD
|