|
United States Environmental
Protection Agency Region
V POLLUTION REPORT |
| Date: |
Friday, July 27, 2007 |
| From: |
James Augustyn/Brian Schlieger, On-Scene
Coordinator |
|
Subject: |
Tittabawassee River Reach D Project
Area Tittabawassee River Dioxin-Reach
D Midland, MI Latitude: 43.6011 Longitude: -84.2386
|
| POLREP No.: |
2 |
Site #: |
B5KF |
| Reporting Period: |
7-23-07 to 7-27-07 |
D.O. #: |
|
| Start Date: |
7/9/2007 |
Response Authority: |
CERCLA |
| Mob Date: |
7/9/2007 |
Response Type: |
Time-Critical |
| Completion Date: |
|
NPL Status: |
Non NPL |
| CERCLIS ID #: |
MID980994354 |
Incident Category: |
Removal Action |
| RCRIS ID #: |
|
Contract # |
|
|
On July 9, 2007, Dow’s contractor began positioning equipment on
a work barge to begin the preparation of driving temporary sheet
piling in the river to delineate the area of highest dioxin
contamination. Dow’s contractor has completed
construction on the HDPE sediment transport pipeline and has
conducted hydrostatic testing of the line. The sediment transport
line is approximately 9,000 feet long and will transport sediment
slurry from the dredge area in the river to the Geo-Tube dewatering
cell.
On-Scene Coordinators (OSC) Jim Augustyn and Brian
Schlieger are providing oversight with assistance from U.S. EPA’s
START Contractor, Weston Solutions,
Inc.
|
|
The following tasks have been completed by Dow's contractors
during the period of July 23-27, 2007:
Monday, July
23: Dow's contractors continued installation of the
temporary sheet pile turbidity barrier above the
bridge. Construction continued on the boardwalk between
the three Geo-Tube containment cells, including preparation of the
Geo-Tube dewatering cell for the application of an asphalt
base. Work continues on establishing functional air
monitoring stations for obtaining continuous baseline air quality
data. A pressure gauge was installed on the HDPE sediment
transport pipeline for hydrostatic pressure testing, and the line
was filled with river water.
Tuesday, July
24: Installation of the temporary sheet piling continued
in the river. Dow mobilized a second crew to expedite the
completion of the sheet pile turbidity barrier in the
river. Application of an asphalt layer in the Geo-Tube
dewatering cell began. Refinement and testing of air
monitoring stations continued.
At approximately 12:10 PM,
U.S. EPA's START contractor notified the OSC that an oil sheen was
developing on the river in the general vicinity of the construction
barge. The Dow Field Coordinator was notified and a
response team was immediately mobilized to contain the sheen with
absorbent boom and pads to prevent further migration
downstream. Later in the day, Dow installed a poly-vinyl
containment boom that will remain on the river until the completion
of the project. The sheen source was identified as coming
from a leak in a hydraulic hose from the ”Vibro-Hammer” used to
drive sheet piling into the river bed.
Wednesday,
July 25: Installation of the temporary sheet piling
continued in the river. Staging and assembly of a second
work barge began. Application of asphalt layers in the
Geo-Tube containment cells continued. The collection of
baseline air quality monitoring began. In addition,
24-hour Summa Canister air samples were collected to compare levels
against field air monitoring equipment.
Thursday,
July 26: Installation of the temporary sheet piling
continued in the river. Staging and assembly of a second
work barge continued. The application of asphalt in the
Geo-Tube containment cells was completed. Baseline air
quality monitoring continued and the 24-hour Summa canister samples
were collected.
Friday, July 27: Installation of
the temporary sheet piling above the bridge is nearly
complete. Staging and assembly of a second work barge
continued. Dow’s contractors continue to prep the
containment cells and began hydro-seeding the perimeter of the
cells. Air monitoring throughout the project area
continues. A visual inspection of the sediment transport
line during hydrostatic testing discovered a suspect “indentation”
on the HDPE line. The defective section of the line will
be removed and replaced. Installation and testing of
turbidity monitors in the river began. A turbidity
monitor will be placed upstream and immediately downstream of the of
the project area. The downstream monitor will measure any
potential turbidity increase resulting from dredging
operations.
|
|
Installation of sheet piling above the bridge is nearly
complete. The sheet piling will be driven down to
established elevations to complete the
installation. Turbidity monitors will be placed in the
river to monitory potential increases in turbidity that may result
from excavation of material from the river bank adjacent to the RGIS
system.
Rip rap and large debris will be mechanically
excavated from the existing RGIS sheet piling within the turbidity
barrier area. The excavated material will be placed over
the RGIS system and allowed to drain. Once sufficiently
free of water, the excavated material will be transported to Dow’s
Salzburg Road Landfill for disposal. When all excavated
material is properly disposed of, a layer of clean gravel will be
placed over the length of the RGIS system.
Construction on
the Geo-Tube containment cells and air monitoring stations will
continue. Geo-Tubes and associated connections to the
sediment transport line will be completed in preparation for
dredging operations to start.
|
|
Once all rip rap and large debris are removed from the work area,
installation of new permanent sheet piling for the RGIS system will
begin. Dredging of contaminated sediment cannot begin
until the permanent sheet piling is in place.
The
second sheet piling crew will continue to install temporary sheet
piling under the bridge. The temporary sheet piling will
be installed along the entire length of the project area and will
end adjacent to the Dow Dam.
|
|
U.S. EPA has completed its review and has provided comments to
Dow on the Draft Work Plan for the site. Dow is preparing
revisions and will resubmit changes by July 31, 2007.
U.S.
EPA has completed its review of the site-specific Health and Safety
Plan (HASP). Dow will incorporate U.S. EPA’s recommendations into
the HASP.
|
| |
Budgeted |
Total To Date |
Remaining |
% Remaining |
|
Extramural Costs
|
| RST/START |
$120,000.00 |
$17,000.00 |
$103,000.00 |
85.83% |
|
Intramural Costs
|
| |
| Total Site
Costs |
$120,000.00 |
$17,000.00 |
$103,000.00 |
85.83% |
* The above accounting of expenditures is an estimate based
on figures known to the OSC at the time this report was written. The OSC
does not necessarily receive specific figures on final payments made to
any contractor(s). Other financial data which the OSC must rely upon may
not be entirely up-to-date. The cost accounting provided in this report
does not necessarily represent an exact monetary figure which the
government may include in any claim for cost recovery.
epaosc.net/tittabawasseeDioxinReachD
|