|
United States Environmental
Protection Agency Region
V POLLUTION REPORT |
| Date: |
Sunday, September 02, 2007 |
| From: |
James Augustyn/Brian Schlieger, On-Scene
Coordinator |
| To: |
Jason El-Zein, ERB
1/RS-1 |
David Chung, OSWER |
|
Al Taylor, MDEQ |
NRC Duty Officer, National Response
Center |
|
Cheryl Howe, MDEQ |
Rick Karl, USEPA |
|
Mark Johnson, U.S. EPA
R5 |
Bill Bolen, ERB 1 |
|
Todd Konechne, Dow Chemical
Company |
Jeff Cahn, USEPA |
|
Jim Sygo, MDEQ |
|
|
Subject: |
Reach O Tittabawassee River
Reach O Midland, MI Latitude: 43.5522 Longitude:
-84.1714 |
| POLREP No.: |
3 |
Site #: |
B5KF |
| Reporting Period: |
August 24 through August 30,
2007 |
D.O. #: |
|
| Start Date: |
8/13/2007 |
Response Authority: |
CERCLA |
| Mob Date: |
8/13/2007 |
Response Type: |
Time-Critical |
| Completion Date: |
|
NPL Status: |
Non NPL |
| CERCLIS ID #: |
MID980994354 |
Incident Category: |
|
| RCRIS ID #: |
|
Contract # |
|
|
On June 27, 2007, U.S. EPA ordered The Dow Chemical Company (Dow)
to negotiate an Administrative Order on Consent, to address removal
of extremely elevated levels of dioxin-contaminated sediment from
within Reach O of the Tittabawassee River near Midland,
Michigan. Dow agreed to the terms of the Order and on
July 12, 2007, the Order was signed by the Regional Administrator
and Dow. For additional background information please see
the site profile. |
|
The following tasks have been completed by Dow’s contractor
during the period from August 24 through August 30,
2007:
• Tree removal and grading along
two areas of the river bank in order to access the Removal
Management Units (RMU) in the Tittabawasse
River.
• Grubbing and grading an area
for the construction of the sediment dewatering and wastewater
treatment operations.
• The
construction of a temporary access haul road along the river and the
installation of a silt fence along the
road.
• Collection and laboratory
analysis of waste characterization samples from the
RMU’s.
• The excavation and staging of
dioxin-impacted sediments from a “hot spot” in the vicinity of RMU
#1.
• The collection and laboratory
analysis of a post removal sample from the “hot spot” after
excavation activities were completed.
The following tasks
are currently on going:
• Collection
of turbidity measurements from meters in the Tittabawasse River in
order to establish background turbidity
measurements.
• Mobilization and
staging of additional heavy equipment and materials to begin driving
sheet piling for the temporary turbidity barrier in RMU
#1&2).
• Continue construction of
the dewatering pad.
|
|
• The installation of temporary sheet
piling, within the Tittabawasse River, to contain the areas of
dioxin contaminated sediment during the excavation activities in the
five RMU’s.
|
|
• Once an RMU has been constructed and
dewaterd, Dow plans to have continuous operations 7 days a week
until the RMU is completed and post removal samples have been
collected. |
| |
Budgeted |
Total To Date |
Remaining |
% Remaining |
|
Extramural Costs
|
| RST/START |
$100,000.00 |
$14,600.00 |
$85,400.00 |
85.40% |
|
Intramural Costs
|
| |
| Total Site
Costs |
$100,000.00 |
$14,600.00 |
$85,400.00 |
85.40% |
* The above accounting of expenditures is an estimate based
on figures known to the OSC at the time this report was written. The OSC
does not necessarily receive specific figures on final payments made to
any contractor(s). Other financial data which the OSC must rely upon may
not be entirely up-to-date. The cost accounting provided in this report
does not necessarily represent an exact monetary figure which the
government may include in any claim for cost recovery.
www.epaosc.net/TittabawasseeRiverReachO
|