|
United States Environmental
Protection Agency Region
V POLLUTION REPORT |
| Date: |
Thursday, September 13, 2007 |
| From: |
James Augustyn/Brian Schlieger, On-Scene
Coordinator |
| To: |
Jason El-Zein, USEPA |
David Chung, OSWER |
|
Al Taylor, MDEQ |
NRC Duty Officer, National Response
Center |
|
Cheryl Howe, MDEQ |
Mark Johnson, U.S. EPA
R5 |
|
Todd Konechne, Dow Chemical
Company |
Jeff Cahn, USEPA |
|
Jim Sygo, MDEQ |
|
|
Subject: |
Removal Action Tittabawassee
River Reach J/K Midland, MI Latitude:
43.5719 Longitude: -84.2006 |
| POLREP No.: |
5 |
Site #: |
B5KF |
| Reporting Period: |
8/31/07 to 9/12/07 |
D.O. #: |
|
| Start Date: |
8/6/2007 |
Response Authority: |
CERCLA |
| Mob Date: |
8/6/2007 |
Response Type: |
Time-Critical |
| Completion Date: |
|
NPL Status: |
NPL |
| CERCLIS ID #: |
MID980994354 |
Incident Category: |
Removal Action |
| RCRIS ID #: |
|
Contract # |
|
|
On June 27, 2007, U.S. EPA ordered The Dow Chemical Company (Dow)
to negotiate an Administrative Order on Consent, to address removal
of extremely elevated levels of dioxin-contaminated soil from an
eroding river bank within Reach JK of the Tittabawasse River near
Midland, Michigan. Dow agreed to the terms of the Order and on July
12, 2007, the Order was signed by the Regional Administrator and
Dow. For additional background information please see the site
profile.
Reach JK will be divided into two areas. The area
along the river bank where contaminated soil will be excavated will
be designated JK-1, and an area further back from the river bank
where clean soil will be used to cap contaminated soil will be
designated JK-2.
On-Scene Coordinator (OSC) Jim Augustyn is
providing oversight with assistance from U.S. EPA’s START
Contractor, Weston Solutions, Inc. |
|
The following tasks are currently on
going:
• Installation of chain link
security fence around the wooded area of
JK-2. • The installation of rip rap along
the shoreline at the northern and southern ends of the JK-1
area. • The installation of an irrigation
system for dust suppression and also to water vegetation planted as
part of the Site Restoration
Activities. • Removal of the soil from the
JK-1 Cut-2 excavation area, and relocating the soil to the JK-2
backfill area (on site).
To view a map that depicts current
site progress, please visit the Document Section of this website and
open the document titled "Site features map".
The following
tasks have been completed by Dow’s contractor during the period from
August 31 – September 12, 2007:
Friday, August 31: Dow’s
contractor completed the excavation and off-site disposal of the
impacted soil within the JK-1 Cut-1 area. Additional
excavation was conducted on the north end and south end of the JK-1
Cut-1 area. An additional 12 inches of surficial soil was removed
from these two areas based on elevated laboratory analytical
results. Upon completion of excavation activities, post-excavation
surface soil samples were collected. The post-excavation
samples were collected to ensure elevated soils would not be
excavated and placed over the JK-2 area as cap
material. Post-removal samples will be collected in JK-1
area after the final cut of soil is excavated and placed in
JK-2.
Saturday - Monday, Sept 1st – 3rd: No site activities
took place due to the Labor Day weekend break.
Tuesday, Sept
4th: Site activities included; delivery of rip rap stone,
the installation of the stone along the southern most portion of the
JK-1 area, surveyors marking the lateral extent of the JK-2
non-wooded area, and the installation of an irrigation
system.
Wednesday, Sept 5th & Thursday, Sept 6th: No site
activities conducted. Awaiting post excavation laboratory
analysis.
Friday, Sept 7th: Laboratory analytical results
indicated elevated dioxin levels in the central portion of JK-1
Cut-1 area remained. Additional excavation activities
were conducted in order to remove soil with elevated concentrations
of dioxin from this central area. Upon completion of the excavation
activities, samples were collected in order to determine if any
residual concentrations of dioxin remained.
Saturday, Sept
8th: Dow’s contractor continued the installation of the site
irrigation system.
Sunday, Sept 9th: No site activities
conducted.
Monday, Sept 10th: Dow’s contractor continued the
installation of the irrigation system. Surveyors collected GPS
coordinates and elevations of the JK-1 Cut-1 area.
Tuesday,
Sept 11th: Surveyors completed the survey activities of the JK-1
Cut-1 area. Dow has received and reviewed the laboratory analytical
data from the post excavation activities. Concentrations
of furan and dioxin are at or near 10 ppt. Dow
contractors continued working on the installation of the rip rap on
the south end of the JK-1 area.
Wednesday, Sept 12th: Dow’s
contractor began Cut-2 within the JK-1 area. The
excavated soil will be used to cap impacted surface soils in the
JK-2 area. Installation of rip rap in the northern area
of JK-1 began. The southern rip rap area has been
completed.
|
|
The following tasks will be
implemented:
• The collection and
laboratory analysis of post removal soil samples from the JK-1 and
JK-2 (non-wooded area) prior to the installation of top soil.
• Importing and installation of topsoil
as part of the site restoration
activities. • Planting of over 200 trees
as part of the site restoration
activities.
|
|
Awaiting comments from the Trustees on the Restoration Work Plan
to finalize seed slection for ground cover.
|
| |
Budgeted |
Total To Date |
Remaining |
% Remaining |
|
Extramural Costs
|
| RST/START |
$100,000.00 |
$27,200.00 |
$72,800.00 |
72.80% |
|
Intramural Costs
|
| |
| Total Site
Costs |
$100,000.00 |
$27,200.00 |
$72,800.00 |
72.80% |
* The above accounting of expenditures is an estimate based
on figures known to the OSC at the time this report was written. The OSC
does not necessarily receive specific figures on final payments made to
any contractor(s). Other financial data which the OSC must rely upon may
not be entirely up-to-date. The cost accounting provided in this report
does not necessarily represent an exact monetary figure which the
government may include in any claim for cost recovery.
|
As of 9/12/07, Dow has removed and transported to the landfill
approximately 23,562 in-place cubic yards of impacted soil from the
Reach JK site. Approximately 24,000 in-place cubic yards of impacted
soil was the estimated total volume to be removed. The following
disposed waste was excavated from the JK-1 Cut #1
area:
8/17/2007 30
loads 540 in-place cubic
yards 8/18/2007 64
loads 1,152 in-place cubic
yards 8/21/2007 76
loads 1,368 in-place cubic
yards 8/22/2007 93
loads 1,674 in-place cubic
yards 8/23/2007 60
loads 1,080 in-place cubic
yards 8/24/2007 103
loads 1,854 in-place cubic
yards 8/25/2007 20
loads 360 in-place cubic
yards 8/27/2007 178
loads 3,204 in-place cubic
yards 8/28/2007 148
loads 2,664 in-place cubic
yards 8/29/2007 180
loads 3,240 in-place cubic
yards 8/30/2007 199
loads 3,582 in-place cubic
yards 8/31/2007 127
loads 2,286 in-place cubic
yards 9/7/2007 31
loads 558 in-place cubic
yards
|
epaosc.net/TittabawasseeReachJK
|